2024 Capital Bond Projects
2024 Capital Bond Update
Planning for Continued Excellence
The Bond Project is broken into three phases – Phase 1, Phase 2, and Phase 3.
Phase 1: Late fall/early winter through Summer 2025.
Phase 2: Summer 2025 through Summer 2026
Phase 3: Summer 2026
Click below to see the progress of Phase I and II projects!
Click here for additional information on the Bond Project and Timeline.
Harborfields High School
-
October 2025 – Small touch ups including patching and painting continues in classrooms and new air conditioning panels were installed.
September 2025 – Bathroom tiling work is ongoing.
August 2025 – Flooring has been installed in the 100, 200, and 400 wings. Painting, lighting, and data runs are ongoing.
July 2025 – Abatement work is ongoing throughout the high school wings. The electrical and plumbing disconnects are completed and installation of the ceiling grid, rerunning of electrical conduits and painting has begun.
-
October 2025 – Metal edge and ladder installation is ongoing.
July 2025 – Roofing work continues over the gym and 200 wing.
April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.
March 2025 – Work has started!
-
Click below to watch a video debuting our new stadium lights!
August 2025 – Work is completed!
July 2025 – Ongoing fiber work in press box.
May 2025 – The stadium lights are in!
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.
April 2025 – Work has started!
-
July 2025 – Existing ashphalt removed and existing courts have been patched and acryclic resurfacer applied. New concrete footings, curbs, and fencing installed. Installation of gates has started. Painting and stripping of two additional existing courts has been completed.
-
August 2025 (continued) – Installation of track continues and striping begins.
August 2025 – Existing track is removed and installation of the new track has begun!
-
July 2025 – Contractors broke down and removed the existing walk-in freezer.
Oldfield Middle School
-
September 2025 – Shingle roof work completed.
August 2025 – The rip and replace of the shingle roof continues. The cupola was power-washed, striped, primed, and received first coat of paint.
July 2025 – Roofers installed curb flashing on the roof area above the gym. They continue to rip and replace the shingle roof on the North side of the building, over the library, and the adjacent wings.
-
September 2025 (continued) – Casework installed in music rooms.
September 2025 – Casework countertops installed.
August 2025 – Installation of corridor lighting and ceiling tiles continues, while ceiling grids are also being installed. Patching, painting, and flooring installation is ongoing.
Thomas J. Lahey Elementary School
-
October 2025 – Brick pier installation continues and the foundation for a new sign is in progress. A perimeter chain link fence was installed.
September 2025 – Installation of brick piers around the perimeter of TJL is ongoing.
-
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.
April 2025 – Work has started!
-
August 2025 – The new parking lot was paved and striped, the existing parking lot was striped and sealcoated, and new sidewalk was poured.
July/August 2025 – Drainage is complete on the North Parking Lot at TJL. Dry wells, piping, crossovers, catch basins, and grates on grade have been installed. The existing blacktop area was milled and surveyed, and new curbing is being laid out. Ongoing removal of existing concreted sidewalks.
-
September 2025 – Basketball court and a new pickleball court was painted and striped.
August 2025 (continued) – Playground and turf installation completed. Ready for play!
August 2025 – Existing playground equipment removed, new playground installation is ongoing.
Washington Drive Primary School
-
August 2025 – The entire parking lot has been paved and sidewalk and curbs have been replaced.
August 2025 – Existing side asphalt parking lot removed and prep began for new parking lot.
-
August 2025 – Installation complete! Playground is open and ready for use.
July 2025 – Installation of new plaground equipment has begun and new turf area is being installed.
-
October 2025 – The storage building is complete.
September 2025 – Construction on a new storage building began.