2024 Capital Bond Projects
2024 Capital Bond Update
Planning for Continued Excellence
The Bond Project is broken into three phases – Phase 1, Phase 2, and Phase 3.
Phase 1: Late fall/early winter through Summer 2025.
Phase 2: Summer 2025 through Summer 2026
Phase 3: Summer 2026
Click below to see the progress of Phase I, Phase II, and Phase III projects!
Click here for additional information on the Bond Project and Timeline.
Harborfields High School
-
Click below to watch a video debuting our new stadium lights!
August 2025 – Work is completed!
July 2025 – Ongoing fiber work in press box.
May 2025 – The stadium lights are in!
_1748633223.jpeg)
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.


April 2025 – Work has started!

-
July 2025 – Existing ashphalt removed and existing courts have been patched and acryclic resurfacer applied. New concrete footings, curbs, and fencing installed. Installation of gates has started. Painting and stripping of two additional existing courts has been completed.



-
August 2025 (continued) – Installation of track continues and striping begins.

August 2025 – Existing track is removed and installation of the new track has begun!

-
August 2026 – Classrooms are substantially complete.

July 2026 (continued) – Abatement commenced in the 300 wing and abatement preparation began in other areas. Completed painting in the 300 wing classrooms and commenced painting in the T wing.
July 2026 – All floor demolition, excluding floors containing asbestos, is completed. Demolition of wall mounted items is contuing, electrical disconnects have begun.
April 2026 – Completed relocation of A/C panels.
October 2025 – Small touch ups including patching and painting continues in classrooms and new air conditioning panels were installed.
September 2025 – Bathroom tiling work is ongoing.

August 2025 – Flooring has been installed in the 100, 200, and 400 wings. Painting, lighting, and data runs are ongoing.

July 2025 – Abatement work is ongoing throughout the high school wings. The electrical and plumbing disconnects are completed and installation of the ceiling grid, rerunning of electrical conduits and painting has begun.

-
July 2025 – Contractors broke down and removed the existing walk-in freezer.

-
March 2026 – Installation complete.
February 2026 – Contractor began installing exterior doors.
-
April 2026 – The contractor repoured the concrete flags damaged during construction.
November 2025 – The contractor has reached substantial completion for the high school roof. Roof passes inspection!
October 2025 – Metal edge and ladder installation is ongoing.

July 2025 – Roofing work continues over the gym and 200 wing.

April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.

March 2025 – Work has started!
-
August 2026 – Completed seating installation.

July 2026 – Demolition and removal of existing auditorium seating is completed.

-
August 2026 (continued) – Framing continues on the east elevation. The monument sign footing is installed, and lintel repair has commenced.

August 2026 – Framing of the facade wall is continuing in preparation for panel installation. The footing of the monument sign has been formed and poured. The fin wall by the main entrance was removed. Painting of the blue panels to green above the main entrance has begun.

July 2026 (continued) – Waterproofing of the south elevation continued. Installation of the helical anchors on the west elevation is ongoing. Repair of the southwest corner is complete.

July 2026 – Repair of the northeast and southeast corners is completed. Existing facade lighting has been removed, and demolition of existing ground sign has begun. Scaffolding is up on the north and south facades and waterproofing has begun.

June 2026 – Installation of helical anchors began on the east facade elevation to reinforce the exterior wall structure.

April 2026 – The contractor took probes of the existing blue facade and door lintels to asses underlying condition of subscurface and to plan for structural reinforcement.
March 2026 – Contractor was on site to obtain column, soffit, and mortar samples for color matching.
-
July 2026 (continued) – Continued to install new ductwork. Installed supplemental steel on the gymnasium ceiling and installed and flashed in curbs on the roof.
July 2026 – Demolition of the existing ductwork and installation of the electrical conduit on the roof have been completed and installation of new ductwork has begun.

April 2026 – The contractor began the low voltage/control rough ins and electrical rough ins. They also began running conduit on the roof.

-
April 2026 (continued) – The contractor completed the corridor ceiling replacement in the guidance hallway, nurse corridor, T wing and 300 wing.

April 2026 – Demolition and installation of the corridor ceilings is underway at the end of the 100 wing and guidance hallway.
-
August 2026 – Main entrance concrete was demolished and prepped for new concrete.
July 2026 – New sidewalk flags installed in the front of the building and new bus loop curbing is complete. Regrading and cleanup work has commenced.

April 2026 – Concrete flags replaced outside of facilities office, tennis courts, and the north walkway. Rip and replacement of the northern half of the bus loop curb is complete.
Oldfield Middle School
-
October 2025 – Edge metal installation continues. West Wing shingle roof completed.
September 2025 – Shingle roof work completed.

August 2025 – The rip and replace of the shingle roof continues. The cupola was power-washed, striped, primed, and received first coat of paint.

July 2025 – Roofers installed curb flashing on the roof area above the gym. They continue to rip and replace the shingle roof on the North side of the building, over the library, and the adjacent wings.

-
August 2026 – Staircase ceiling and lighting have been installed, scaffolding has been taken down, and classrooms are substantially complete.

July 2026 (continued) – Abatement completed in the first set of classrooms and new ceiling grid installation is ongoing. Abatement removal began in second set of classrooms.

July 2026 – All demolition that is not being abated is complete. Abatement contractor mobilized and set up containment for the 200 wing and commenced abatement.
October 2025 – New AC panels were installed.
September 2025 (continued) – Casework installed in music rooms.

September 2025 – Casework countertops installed.

August 2025 – Installation of corridor lighting and ceiling tiles continues, while ceiling grids are also being installed. Patching, painting, and flooring installation is ongoing.

-
October 2025 – Installation of new 2x2 ceiling tile system to replace old 4x4 ceiling system.

-
March 2026 – Installation complete.
February 2026 – Contractor began installing exterior doors.
-
August 2026 – Irrigation and regrading of the center of the field are underway. Contractor continued preparation for the paving of the track and ADA ramp.

July 2026 (continued) – Contractor prepped for the concrete curb pour and new asphalt track. Continuing installation of new drainage and go fence poles.
July 2026 – Installation of new dry well and associated connections/piping continue. Layout of the new track and field has begun. Drainage installation continued.

June 2026 – Demolition of the existing track is underway. Silt fencing was installed for erosion control. Removal of unsuitable material below grade to an off-site facility.

May 2026 – Temporary fencing installed around the track in preparation for the future work.
Thomas J. Lahey Elementary School
-
January 2026 (Continued) – Ground sign installed.

January 2026 – Completed installation of slide gates and pedestrian gates.

November 2025 – Contractor completed ornamentall fence and installed the gate posts.

October 2025 (continued) – Contractor commenced installation of the ornamental fence and edge metal installation.

October 2025 – Brick pier installation continues and the foundation for a new sign is in progress. A perimeter chain link fence was installed.

September 2025 – Installation of brick piers around the perimeter of TJL is ongoing.

-
December 2025 – Passed final inspection.
November 2025 – Completed edge metal installation and finished all open items. Awaiting final inspection.
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.


April 2025 – Work has started!

-
August 2025 – The new parking lot was paved and striped, the existing parking lot was striped and sealcoated, and new sidewalk was poured.

July/August 2025 – Drainage is complete on the North Parking Lot at TJL. Dry wells, piping, crossovers, catch basins, and grates on grade have been installed. The existing blacktop area was milled and surveyed, and new curbing is being laid out. Ongoing removal of existing concreted sidewalks.

-
September 2025 – Basketball court and a new pickleball court was painted and striped.

August 2025 (continued) – Playground and turf installation completed. Ready for play!
August 2025 – Existing playground equipment removed, new playground installation is ongoing.

-
March 2026 – Contractor began installing exterior doors.
-
August 2026 (continued) – All classrooms are substantially complete.

August 2026 – Smartboards installed. Contractor completed C & D wing classrooms.
July 2026 (continued) – Completed abatement and paint prep in all classrooms. Received all ceiling tiles and began installation.

July 2026 – All plumbing and electrical disconnects are complete. Demolition of existing ceilings, flooring, and wall-mounted items is ongoing. Wall preparation and painting are continuing. Abatement underway in the C & D wings.

Washington Drive Primary School
-
December 2025 (continued) – Lighting fixtures installed. Parking lot light installation completed.
December 2025 – New parking lot light poles installed.

November 2025 – Striping of front parking stalls completed.

The electrical contractor began trenching and pre-wiring for the new parking lot lights near Treasure Cove.

August 2025 – The entire parking lot has been paved and sidewalk and curbs have been replaced.

August 2025 – Existing side asphalt parking lot removed and prep began for new parking lot.

-
August 2025 – Installation complete! Playground is open and ready for use.
July 2025 – Installation of new plaground equipment has begun and new turf area is being installed.

-
October 2025 – The storage building is complete.

September 2025 – Construction on a new storage building began.


