2024 Capital Bond Projects
2024 Capital Bond Update
Planning for Continued Excellence
The Bond Project is broken into three phases – Phase 1, Phase 2, and Phase 3.
Phase 1 construction: Anticipated to start late fall/early winter through summer 2025.
Click below to see the progress of Phase 1 projects!
Click here for additional information on the Bond Project and Timeline.
July 2025 – Abatement work is ongoing throughout the high school wings. The electrical and plumbing disconnects are completed and installation of the ceiling grid, rerunning of electrical conduits and painting has begun.
July 2025 – Roofing work continues over the gym and 200 wing.
April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.
March 2025 – Work has started!
July 2025 – Ongoing fiber work in press box.
May 2025 – The stadium lights are in!
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.
April 2025 – Work has started!
July 2025 – Existing ashphalt removed and existing courts have been patched and acryclic resurfacer applied. New concrete footings, curbs, and fencing installed. Installation of gates has started. Painting and stripping of two additional existing courts has been completed.
July 2025 – Contractors broke down and removed the existing walk-in freezer.
-
July 2025 – Abatement work is ongoing throughout the high school wings. The electrical and plumbing disconnects are completed and installation of the ceiling grid, rerunning of electrical conduits and painting has begun.
-
July 2025 – Roofing work continues over the gym and 200 wing.
April 2025 – Certain roof areas have been ripped down to decking, insulation replaced, rubber membrane completed. The raised portion of a particular roof area has been ripped and replaced and rubber membrane installed.
March 2025 – Work has started!
-
July 2025 – Ongoing fiber work in press box.
May 2025 – The stadium lights are in!
April 2025 (continued) – All walkway light bases have been installed and trenching has begun. Crews are finishing trenching, dropping conduits, and refilling between remaining walkway light bases.
April 2025 – Work has started!
-
July 2025 – Existing ashphalt removed and existing courts have been patched and acryclic resurfacer applied. New concrete footings, curbs, and fencing installed. Installation of gates has started. Painting and stripping of two additional existing courts has been completed.
-
July 2025 – Contractors broke down and removed the existing walk-in freezer.
July 2025 – Roofers installed curb flashing on the roof area above the gym. They continue to rip and replace the shingle roof on the North side of the building, over the library, and the adjacent wings.
-
July 2025 – Roofers installed curb flashing on the roof area above the gym. They continue to rip and replace the shingle roof on the North side of the building, over the library, and the adjacent wings.
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.
April 2025 – Work has started!
July 2025 – Drainage is complete on the North Parking Lot at TJL. Dry wells, piping, crossovers, catch basins, and grates on grade have been installed. The existing blacktop area was milled and surveyed, and new curbing is being laid out. Ongoing removal of existing concreted sidewalks.
-
April 2025 (continued) – Ripped and replaced insulation down to decking in specific areas. Rubber roof membrane installed.
April 2025 – Work has started!
-
July 2025 – Drainage is complete on the North Parking Lot at TJL. Dry wells, piping, crossovers, catch basins, and grates on grade have been installed. The existing blacktop area was milled and surveyed, and new curbing is being laid out. Ongoing removal of existing concreted sidewalks.
July 2025 – Installation of new plaground equipment has begun and new turf area is being prepped.
-
July 2025 – Installation of new plaground equipment has begun and new turf area is being prepped.